CNOOC completes maintenance at Tianjin LNG terminal xinde marine news 2019-05-17 17:26


CNOOC Gas & Power has recently completed maintenance works at its Tianjin liquefied natural gas import terminal. 
 
The maintenance was completed during a four-day period before the gas flows to the national transmission network resumed on April 27, the company said in a statement.
 
Terminal operator said it has completed over 40 checks during the maintenance shutdown ‘improving the health of its equipment, following a busy winter period.
 
According to the company, a sub-station ball valve replacement has been completed, including various machinery, instruments and electrical components overhauls. Leak points at the high-pressure compressor were welded while work has also been carried out on the pipeline.
 
CNOOC noted that it was also the first time the maintenance at the Tianjin LNG has been completed independently.
 
Source:LNG World News

The opinions expressed herein are the author's and not necessarily those of The Xinde Marine News.

Please Contact Us at:

admin@xindemarine.com


展开全文

Related Posts

Future of LNG Shipping: A Bright Horizon

xinde marine news Chen Yang2024-07-16

Vitol invests in future of LNG bunkering by securing three LNG Bunkering Vessels

Vitol2024-07-05

Decarbonization Countermeasures between Sallaumlines & SunRui

SunRui2024-05-23

Nautical SUNRISE Project to facilitate R&D of the largest Offshore Floating Solar power plant in

xinde marine news2024-03-04

COSCO SHIPPING Heavy Industry delivered China's first MOSS Spherical LNGC converted into FSRU project

xinde marine news2024-01-17

Asia’s First Wind-Rotor System Start Commissioning by China

COOEC2024-01-16