CNOOC to start Tianjin-Inner Mongolia pipeline follow-up project in Sep xinde marine news 2019-08-29 09:22


China National Offshore Oil Corp (CNOOC) will kick off the follow-up project of the first phase of Tianjin-Inner Mongolia natural gas pipeline from late September, according to the state-backed China News Service 
 
The 1,279-kilometer (km) pipeline is designed to connect the liquefied natural gas (LNG) terminal in Tianjin, coal-to-gas plants in Inner Mongolia and the densely-populated capital city of Beijing and its surrounding regions, with annual transmission capacity of 20 billion cubic meters 
 
Construction on the first phase of the project, linking Tianjin LNG terminal to pipelines in Hebei province in a total length of 413.5 km, started in November and has completed 31.5 km so far 
 
The rest of the first phase, totalling 382 km, is expected to be completed by end-November 2020 and enable 14 million cubic meters of gas from imported cargos in Bohai regions to be moved to the Beijing-Tianjin-Hebei region, China News Service said. 
 
Source:sxcoal

The opinions expressed herein are the author's and not necessarily those of The Xinde Marine News.

Please Contact Us at:

admin@xindemarine.com


展开全文

Related Posts

COSCO Shipping’s Major Europe Move: Extending Its Network Beyond the Port into the Hinterland

xinde marine news2026-01-12

EVERGREEN CONFIRMS FLEETWIDE ROLLOUT OF INMARSAT NEXUSWAVE

xinde marine news2026-01-08

PIL marks New Year's Eve by sponsoring Humanity Matters' Gaza Relief efforts

xinde marine news2026-01-05

Corvus Energy Secures Record Order for Seven Fully Electric CMAL Ferries

xinde marine news2025-12-22

bound4blue lands US$44M from investors eyeing wind power as maritime’s most scalable solution for f

xinde marine news2025-12-11

Advanced Polymer Coatings wins deal to coat two new build methanol tankers with Fratelli Cosulich

xinde marine news2025-12-10